M13 — Meta Plan (milestone grouping)

Companion to M13_FRONTEND_SPEC.md. This is the cross-milestone plan; per-milestone detail lives in M13a_PLAN.md, M13b_PLAN.md, M13c_PLAN.md.

Status: planning (post-M11, parallel to M12) Goal: ship a v1 multi-tenant admin UI that replaces dlq.html and adds CRUD + live-tail + audit + auth surfaces, in a single admind Go binary that embeds a Vite+React 19 SPA.


0. Why milestones, not one big plan

The original M13 plan (workstream-as-primary-axis, 9 workstreams) assumed one engineer ships end-to-end. In practice you stop and review between surfaces — and you want each stop to be a shippable artifact, not "we have some auth working but no UI yet".

The milestone split lets you:

Stop after What you have Why stop here
M13a authd + web skeleton + login works "Is the design right? Is the auth model right? Is the SPA architecture right?" — review before committing to feature work.
M13b Companies + Sources + Telegram CRUD ~80% of operator value. The customer can self-onboard, set up sources, configure telegram. Live tail + DLQ + audit can wait.
M13c Live tail + DLQ + Audit + K8s + E2E Full v1. Replaces dlq.html, ships Playwright gate, K8s-ready.

Each milestone flips one SPEC.md row. Each has its own M13x_PLAN.md with workstreams, estimates, and per-milestone DoD.


1. Milestone overview

                ┌──────────────┐
                │  M13.0 spec  │   (this PR — no code)
                │  + API       │
                └──────┬───────┘
                       │
                       ▼
                ┌──────────────┐
                │   M13a       │   ~5-6 days
                │  authd +     │
                │  web shell   │
                │  + JWT gate  │
                └──────┬───────┘
                       │
                       ▼
                ┌──────────────┐
                │   M13b       │   ~7-8 days
                │  CRUD:       │
                │  Companies   │
                │  Sources     │
                │  Telegram    │
                └──────┬───────┘
                       │
                       ▼
                ┌──────────────┐
                │   M13c       │   ~7-9 days
                │  Live tail   │
                │  DLQ         │
                │  Audit       │
                │  K8s         │
                │  Playwright  │
                └──────────────┘

Total estimate: ~19-23 days with one engineer. Can be parallelized with a second engineer at M13b (one on Companies, one on Sources).


2. Milestone summaries

M13.0 — Spec & API contract

  • M13_FRONTEND_SPEC.md
  • M13_API_CONTRACT.md
  • No code. This PR. No DoD beyond "specs reviewed and committed".

M13a — authd + web skeleton + JWT gate

  • cmd/authd/ — JWT IdP service on :8804, all 7 endpoints.
  • web/ — Vite + React 19 + shadcn/ui + TanStack Query + RHF + Zod. Login page works end-to-end. Other routes render "coming soon".
  • admind modified to require JWT on all /v1/* endpoints (except /health, /metrics).
  • Plan: M13a_PLAN.md.

M13b — CRUD

  • Companies: list, detail, create, edit, suspend (super); read-only (tenant).
  • Sources: list, detail, create, edit, rotate secret, suspend. One-time secrets modal.
  • Telegram: bot config, invite codes, bindings list.
  • All forms validate; audit log writes; error toasts.
  • Plan: M13b_PLAN.md.

M13c — Ops surface + K8s + E2E

  • Live tail: SSE feed, filter bar, drill-in modal, pause-on-scroll.
  • DLQ: list, detail, replay, discard. Replaces dlq.html.
  • Audit log viewer.
  • K8s manifests for admind and authd (carry from M12 W1).
  • Playwright E2E happy path green in CI.
  • Plan: M13c_PLAN.md.

3. Cross-cutting concerns

These live in the spec but are operationally tested in M13c:

  • Single binary: admind embeds the SPA via embed.FS. Target size: < 60 MB.
  • No CORS: SPA is served by admind itself. authd is same-origin via service discovery.
  • OpenAPI client gen: pnpm run gen:api in CI on every Go API change. Type drift fails the PR.
  • Tenant isolation: backend enforces WHERE company_id = $1 for tenant-admins. Tested in Playwright with a cross-tenant 403 check.
  • Audit immutability: every state-changing call writes to audit_log. The viewer is read-only.

4. Dependencies

From What Status Affects
M11 gRPC ingest stable, F2 publish counter ✅ done M13c (live tail source)
M12 W1 K8s manifests for admind and authd ⏳ in flight M13c W7 (K8s manifests)
Postgres auth schema + tables to be created in M13a W1 M13a
Redis rate-limit counters for authd login ✅ already in stack M13a
NATS tailhub for in-memory SSE feed (M13c) ✅ already exists M13c
SMTP (optional) magic-link email NOT required for v1 (psql fallback) M13a (best-effort)

5. Parallelism with M12

When What runs in parallel
M13a W1-W2 M12 W1 (K8s manifests) — independent
M13b W1-W3 M12 W2 (NATS cluster) — independent
M13c W7 M12 W3-W4 (Helm + 50k/s bench) — blocks K8s manifest merge

M13 does not block M12. M12 W5 (M11 prod gate on K8s) is independent of M13. The two milestones converge at "single PR that ships v1 with K8s + frontend" but the workstream branches don't have to.


6. Definition of done — whole M13

  • All 3 sub-milestones (M13a, M13b, M13c) have their individual DoD checked.
  • cmd/authd/ exists, builds, runs, healthy on :8804.
  • cmd/admind/ builds with embedded SPA, < 60 MB.
  • Playwright happy-path green in CI for 3 consecutive runs.
  • Tenant-isolation 403 test green in CI.
  • M13_VERIFICATION.md published with: screenshots of the 6 modules, the Playwright run log, the tenant-isolation test, the binary size, and the bundle breakdown.
  • SPEC.md M13a, M13b, M13c rows flipped to ✅ shipped YYYY-MM-DD.
  • cmd/admind/ui/dlq.html removed.
  • Demo to a real customer (or internal stakeholder) and signed off.

Next step: commit the 3 docs from M13.0, then start M13a W1 (authd).